Q.
1
-
A
Standard costs are based on scientific analysis and engineering studies while estimated costs are based on historical basis.
-
B
Standard cost emphasis is on “what cost will be” while estimated cost emphasis is on “what cost should be”.
-
C
Standard costs are more frequently revised compared to estimated cost.
-
D
Estimated costs are more stable than standard costs.