Q.
1
  • A

    Standard costing is a system where pre-determined costs are used for control of entire organization.

     

  • B

    Standard may be expressed in quantitative and monetary measures

     

  • C

    Only adverse variances are investigated intensively

     

  • D

    Standard is determined for each element of cost.