Q.
1

Statement (II): The duration of a project is not always the same as the duration of its critical path.

Statement (III): The Earliest start and finish times of an activity are based on the condition that every activity will not be started and finished as early as possible.

  • A

    Find the correct code for given statements being correct or incorrect.

     Statement (I) and (II) are correct but (III) is not correct. 

     

  • B

    Statement (I) and (III) are correct but (II) is not correct.

  • C

    Statement (I) is correct but (II) and (III) are not correct.

  • D

    Statement (II) is correct but (I) and (III) are not correct.