Q.
1

A.Cash flow estimation

B.Identify discounting rate

C.Project selection decision

D. Determination of NPV

Choose the correct answer from the options given below:

  • A

    A, B, C and D

  • B

    A, B, D and C

  • C

    D, A, B and C

  • D

    B, A, D and C