Q.
1
List – I |
List – II |
a. Any physically identifiable part of a project | i. Network |
b. The terminal point of an activity | ii. Event |
c. The longest chain in the Network | iii. Activity |
d. Logically and sequentially connected arrows and nodes | iv. Critical path |
-
A
a b c d
i ii iii iv
-
B
iii ii iv i
-
C
ii iv i iii
-
D
iv i ii iii