Q.
1

List – I

List – II

a. Any physically identifiable part of a project i. Network
b. The terminal point of an activity ii. Event
c. The longest chain in the Network iii. Activity
d. Logically and sequentially connected arrows and nodes iv. Critical path
  • A

    a        b       c        d

    i         ii        iii       iv

     

     

     

  • B

    iii       ii        iv      i

  • C

    ii        iv       i        iii

  • D

    iv       i        ii        iii