Q.
1
-
A
Budgeted labour Costs – Actual labour costs
-
B
(Standard Hours – Actual Hours) x Actual Wage Rate
-
C
(Standard Wage Rate – Actual Wage Rate) x Actual Hours Worked
-
D
(Standard Wage Rate – Actual Wage Rate) x Standard Hours Worked