Q.
1
Statement (II): The duration of a project is not always the same as the duration of its critical path.
Statement (III): The Earliest start and finish times of an activity are based on the condition that every activity will not be started and finished as early as possible.
-
A
Find the correct code for given statements being correct or incorrect.
Statement (I) and (II) are correct but (III) is not correct.
-
B
Statement (I) and (III) are correct but (II) is not correct.
-
C
Statement (I) is correct but (II) and (III) are not correct.
-
D
Statement (II) is correct but (I) and (III) are not correct.